Pinnacle Memorial Hospital Construction Site Update October

(New) Pinnacle Memorial Hospital Construction Site Update – October 2017
Monthly Update

1701 Old Memorial Way, York, PA 17408

Please see below summary of work taking place at the Pinnacle York Memorial Hospital site:

  • Micropile work is continuing in the basement and the first floor next week.  CUP micropiles to begin within the next few weeks.  Scheduled completion for all micropiles is November 29.
  • Concrete foundations are scheduled to begin 10/23, pending permit approval
  • McClure and PCS have set up job trailers on site.
  • Loucks Road pole relocation is complete except for a few additional poles that were found to need to be relocated.
  • Quandel is in the process of de-scoping the core and shell bids and will award within the next few weeks.
  • Work has begun along Loucks Road.  York Excavating is excavating the pond.
  • York Excavating has been awarded the site contract and is continuing excavation around the pile caps, CUP and remainder of the basement
  • Final Core & Shell permit drawings will be delivered 10/23