  • Micropile work is underway in the basement and will begin on the first floor next week.  Scheduled completion for hospital micropiles is November 1.
  • Temporary fencing has been installed around the building footprint
  • McClure and Heim are beginning to set up their job trailers.
  • Loucks Road pole relocation was placed on hold due to crews going to help with the hurricane in Florida.  Work is scheduled to start up again on 9/27 and complete by 10/13
  • Quandel has awarded micropiles, hospital concrete foundations, structural steel, architectural precast, and elevators
  • Foundations are scheduled to begin mid to end of October
  • Loucks/Roosevelt/Route 30 work has been awarded to York Excavating and a pre-installation meeting took place yesterday.  Work will begin on October 2.
  • York Excavating has delivered HDPE piping for the Loucks Road work
  • Quandel has additional staff on site – Tony Achampong as an APM and Pat Miele as a PA
  • Core and Shell documents were submitted to the township for permit review on 9/12